Church Rd. Ditching and Culvert Work

Please Use Caution Around Road Maintenance Activities
Seal

The Town of Readfield has contracted with Pike Industries to perform ditching and culvert work on Church Rd. the week of October 3-7, 2022.  Work will consist of several hundred feet of ditch cleaning at various locations and the repair of replacement of several driveway culverts.  Pike Industries is a well-known and experienced company and will use due care and caution when performing the work.  We ask the motorists please use due care and caution when in the work area.

Town of Readfield Maintenance Staff will be overseeing the work which is identified in detail below.  This work is being performed as part of our routine maintenance schedule and in preparation for paving of Church Rd. in the spring.  Vegetation management (tree trimming and brush removal) will be performed before paving and property owners will have the opportunity to do their own clearing provided it meets the necessary criteria for road safety and maintenance.  Additional notice will be provided in advance of vegetation management work.

Church Road, Northbound - Rt. 17 to Mount Vernon Town Line:

  • Cemetery ditching in front of Rock Wall - Center Access cut out material, allow water flow.
  • #141 Church Road, First property access: completely clogged or missing culvert, needs replacement.  Second(main) access:  clogged culvert - unclog.  Cut back roadside material and re-ditch entire property frontage as well as just north of second driveway  (1) One 30’x18” culvert.

Church Road, Southbound - Mount Vernon Town Line to Rt. 17

  • Town Line South to #414 Church Road, material cut back and re-ditch.  Cross Culvert prior to #414 is clogged.  Unclog & install riprap catch basin.
  • #410 Church Road, cross culvert is clogged, cannot find exit on east side of Church Road, Unclog & install riprap catch basin.
  • Continue material removal and re-ditching from #410 to cross culvert prior to #374.
  • Adjacent #141 south to #128 Church Road. cut back material and re-ditch.
  • Ditching beginning at #58 Church Road to #44 Church Road.  Replace clogged metal culvert #58.  Replace metal/clogged culvert #52 main property access; replace metal/clogged culvert second property access #52, (3) Three 20’x15” culverts.
  • Re-ditching from #34 Church Road to #30 Church Road, #30 has clogged plastic culvert, Unclog culvert.
  • #22 Church Road, first property access, plastic culvert, reset culvert.  Middle property access culvert, metal and clogged, replace.  Third/main property access metal culvert clogged, replace.  Re-ditch length of #22 Church Road.  (1) One 20’x15” culvert, (1) One 25’x15” culvert.
  • #8 Church Road, main property access metal culvert, set too high but not rotted, replace.  Both secondary property access metal culvert are rotted, replace.  (1) One 30’x15” culvert, (1) One 8’x15” culvert, (1) One 10’x15” culvert.
  • #1149 Rt 17, driveway access on Church Road.  Metal/Clogged culvert.  Replace.  (1) One 30’x15” culvert.

Please contact me HERE with any questions.

Thank you,

 Eric Dyer, Town Manager / Road Commissioner